Conejo Standby Diesel Generators:
- Owner: Calleguas Municipal Water District
- Cost: $4,500,000 (+/-)
Conejo Standby Diesel Generator facility was constructed to provide power to Calleguas' several critical facilities during power outages. These facilities include Conejo Pump Station, Linder Pump Station No.2, and Water Filtration Plant located near Calleguas' main headquarters.
Perliter & Ingalsbe provided a complete engineering services involving complex mechanical, electrical, structural, civil, and control designs.
Major Components and Special Features:

- Four 2.0 MW, 4160VAC, 3Phase, 1200A diesel operated generators to power multiple facilities, including:
- Lindero Pump Station No.2 comprised of four pumps with 350HP through 700HP, 4160VAC motors, 480VAC switchboard, and 120/240VAC panel board serving control valves, air compressor, and lighting
- Conejo Pump Station comprised of five pumps with 250HP through 500HP, 2400VAC motors, 480VAC switchboard, and 120/240VAC panel board serving control valves, air compressor, and lighting
- Water Filtration Plant load comprised of 480VAC, 3Phase, 400A Switchboard serving ozone generators, filters, chemical building, clearwell, and WW recovery pump station

- Generator appurtenances and auxiliary devices
- Paralleling switchgear, 4160VAC
- Automatic transfer switches
- Three 10,000 gallon diesel storage tanks
- Waste oil storage tank
- Air compressor
- Bridge crane
- Concrete tilt-up building with special architectural treatment
- Controls and instrumentation